July 7, 2025 · 12 min read
Groundwater NOC in Haryana (HWRA): Complete 2026 Guide for Industries & Builders
Groundwater NOC in Haryana (HWRA): Complete 2026 Guide for Industries & Builders
Here is the mistake that costs Haryana businesses months: they search for "CGWA NOC" and try to apply on the national Bhu-Neer portal. In Haryana, that application goes nowhere. Since 2020, groundwater extraction permissions in Haryana are issued by the Haryana Water Resources (Conservation, Regulation and Management) Authority — HWRA, not by the Central Ground Water Authority.
If your factory, warehouse, hotel, hospital, group-housing project or commercial complex in Gurugram, Faridabad, Panipat, Sonipat, Manesar, Bahadurgarh or anywhere else in Haryana draws groundwater, you need an HWRA NOC. This guide covers the portal, the process, the documents, the fees and the compliance — the Haryana way.
Who Is HWRA and Why Not CGWA?
The Haryana Water Resources Authority was constituted under Section 3 of the Haryana Water Resources (Conservation, Regulation and Management) Authority Act, 2020. Because Haryana enacted its own groundwater legislation, the Central Ground Water Authority stepped back — HWRA is now the sole body that grants permission to abstract groundwater in the state. This is why a "CGWA NOC Haryana" search is misleading: the certificate you actually need is an HWRA NOC.
Who Needs an HWRA NOC in Haryana?
- Manufacturing units and industries in Manesar, Bawal, Bahadurgarh, Panipat, Yamunanagar and Faridabad
- Group housing, townships and commercial/IT projects across Gurugram and Faridabad
- Hotels, banquet halls, hospitals, schools and malls drawing groundwater
- Infrastructure and construction projects needing water for the build phase
- Packaged drinking water, bottling and food-processing units
Individual domestic users and farmers are outside HWRA's permit net. Everyone else drawing groundwater for commercial or bulk use needs permission.
The Over-Exploited Reality in Haryana
Haryana is one of India's most groundwater-stressed states — a large share of its assessment blocks are Over-Exploited, particularly across the National Capital Region. That matters because HWRA scrutiny is far tighter in Over-Exploited and Critical blocks: expect a mandatory impact assessment with groundwater modelling, aggressive recharge conditions, and restrictions on fresh groundwater for new projects where a piped supply exists.
How to Apply for an HWRA NOC — Step by Step
Step 1 — Register on the HWRA Portal
Create your applicant account on the HWRA portal at hwra.org.in (the "NOC to Abstract Ground Water" module). Enter entity, project and contact details to generate your login.
Step 2 — Prepare the Technical Documents
For most industrial and infrastructure projects — and mandatorily above 500 KLD — you need an Impact Assessment Report with groundwater modelling prepared by an accredited agency, along with a rainwater-harvesting plan and, where applicable, a water audit.
Step 3 — Attach Statutory NOCs
HWRA expects supporting clearances: the State Pollution Control Board consent, a water-denial / non-availability certificate from the local supply agency (proving piped water is not available), and — if the site is within 500 metres of a notified wetland — a wetland authority NOC.
Step 4 — Submit and Pay
Upload everything and submit online. HWRA also requires a 90-day advance groundwater tariff to be deposited as security along with the applicable fee.
Step 5 — Scrutiny and Grant
HWRA reviews the file, may seek clarifications or a site check, and — on satisfaction — issues the permission with its extraction quantum and conditions. Expect roughly 120 days end-to-end for a clean application.
HWRA Documents Checklist
- Entity KYC — PAN, GST, incorporation, authorisation letter
- Land ownership / lease papers and site plan with coordinates
- Impact Assessment Report with groundwater modelling (Over-Exploited / Critical / Semi-Critical, and all >500 KLD)
- Rainwater harvesting plan and water audit report
- State Pollution Control Board consent (CTE / CTO)
- Water non-availability / denial certificate from the supply agency
- Wetland authority NOC if within 500 m of a wetland
HWRA Fees & Validity
HWRA fees are structured by user type and category and are higher than the central fee — industrial/direct-user government fees run into the range of tens of thousands to over a lakh depending on category, with renewal typically half of the fresh fee. On top of the fee, you deposit a 90-day advance tariff based on your sanctioned demand. A compliance report must be filed before validity expires. Because HWRA revises its fee and tariff schedule periodically, confirm the current figures on hwra.org.in before you deposit.
Haryana vs the National System — Don't Confuse Them
If you also operate units in CGWA states, remember the systems differ. Our Bhu-Neer portal guide covers the central process, while states like Uttar Pradesh run yet another portal. Haryana stands on its own with HWRA. For the big picture, see our complete CGWA NOC guide.
Frequently Asked Questions
1. Is CGWA NOC or HWRA NOC required in Haryana?
HWRA. Since the Haryana Water Resources Authority Act, 2020, groundwater NOCs in Haryana are issued by HWRA, not CGWA. Applications are filed on hwra.org.in.
2. How long does an HWRA NOC take?
Around 120 days for a complete application, and longer in Over-Exploited blocks where groundwater modelling and additional scrutiny apply.
3. What is the 90-day advance tariff in HWRA?
HWRA requires applicants to deposit an advance groundwater tariff — roughly 90 days of usage based on sanctioned demand — as a security along with the application fee.
4. Do builders and group-housing projects in Gurugram need an HWRA NOC?
Yes. Group housing, townships, commercial and IT projects in Gurugram and Faridabad that use groundwater must obtain HWRA permission, usually with an impact assessment given the Over-Exploited status of the NCR blocks.
5. Is groundwater modelling mandatory for HWRA?
It is mandatory for projects above 500 KLD and for sites in Over-Exploited, Critical and Semi-Critical categories, prepared by an accredited agency.
Need an HWRA NOC in Haryana?
Bhoojal Survey prepares HWRA-grade impact assessments and manages the full application on hwra.org.in — from survey to grant to compliance — for industries and builders across Gurugram, Faridabad, Panipat and the wider NCR. Call +91-9691858058 or get a free eligibility check.